BİRECİK HEPP (6x 112 MW)

BİRECİK HEPP (6x 112 MW)

Mechanical Erection of 6 turbines, generators and auxiliaries manufactured by ALSTOM, VA-TECH SULZER ESCHER WYSS and ALSTOM ASEC ENERGY.

Other Works in the Scope of This Project

Basic and detailed design, equipment supply, panel manufacturing, civil work, erection,test and commissioning of 1 No 380 kV line feeder  on turn-key basis.

  • Client: GAMA A.Ş.
  • Place : ŞANLIURFA
  • Date: 2001